L3Original starter · Free

Supply chains, capacity and options

Part of the Management Trainee learning and recruiting path. Read the explanation and example, attempt the task, then open the self-check.

Understand

A process is constrained by its bottleneck. Locate whether procurement, production, delivery or staffing limits growth. Compare cost, speed, quality and feasibility.

Worked example

Preparation at 80/hour, production at 50 and delivery at 70 caps throughput near 50. Expanding delivery alone does not remove production constraints.

Examples and numbers are educational, not employer questions, live market data or hiring criteria.

Practise and keep your output

Map a three-stage process and compare staffing, outsourcing and menu changes by cost, benefit and risk.

Keep inputs and sources, assumptions, steps, results and uncertainties in your own document. Attempt independently before checking below.

After attempting: answer and self-check

Bottlenecks can move. Use consistent periods and units, and distinguish capacity from demand.

Official channels and further reading

Pathline authors these starter lessons. These supplementary field links do not imply provider review or endorsement. Confirm Hong Kong availability and eligibility separately.